Given the following information regarding a project involving an initial public offering (IPO):
Activities Description Duration (weeks) Predecessors
a. Check feasibility 3 —
b. Determine funding 1 —
c. Find possible banks 3 a
d. Select two possible 4 a
e. Interview two banks 4 b
f. Analyze funding costs 5 b
g. Determine chance of success 2 c ,e
h Sign contract 3 f
a) Draw the network.
b) What is the critical path?
c) Calculate the float for each activity.
d) What is the effect on the project if activity e (approvals) takes an extra week? Two extra weeks? Three extra weeks?

Answers: 3

Answers

  • Answer posted by: jalenthomas2208

    the correct answer is d. wealthy colonists to take care of the less fortunate. hope this

  • Answer posted by: pettygirl13
    General education? that is the only one i could think of.
  • Answer posted by: purplefish53

    answer; commerce clearing house;

Do you know the correct answer?
Given the following information regarding a project involving an initial public offering (IPO): Acti...

Popular questions